Le projet Kamoa-Kakula Copper - une coentreprise entre Ivanhoe Mines (39,6%), Zijin Mining Group (39,6%), Crystal River Global Limited (0,8%) et le gouvernement de la République démocratique du Congo (20%) - a été indépendamment, classé par le consultant international en exploitation minière Wood Mackenzie, comme la plus grande découverte de cuivre à haute teneur non développée au monde. C'est un très grand gisement de cuivre stratiforme, proche de la surface, avec des zones d'exploration potentielles adjacentes dans la ceinture de cuivre d'Afrique centrale, à environ 25 kilomètres à l'ouest de la ville de Kolwezi et à environ 270 kilomètres à l'ouest de la capitale provinciale de Lubumbashi.

Première production de cuivre attendue dans moins d’un an

Initial production at the Kakula Mine processing plant is scheduled for Q3 2021. Kakula is projected to be the world’s highest-grade major copper mine, with an initial mining rate of 3.8 million tonnes per annum (Mtpa) at an estimated average feed grade of more than 6.0% copper over the first five years of operation. Kakula is the first of multiple, planned, high-grade mining areas on the 400-square-kilometre Kamoa-Kakula mining licence.

The Kakula Mine will have one of the most favourable environmental footprints of any tier-one copper mine worldwide. La mine sera alimentée par de l’hydro-électricité propre et durable. Elle sera parmi les émetteurs de gaz à effet de serre les plus faibles au monde par unité de cuivre produite. Kakula also will have a relatively small surface footprint, as approximately 55% of the mine’s tailings will be pumped back into underground workings.

All long-lead items for Kakula’s initial 3.8-Mtpa processing plant now have been delivered to site with the exception of the transformers, which are currently en route and expected around the third week of October.

On 1 octobre 2020, Ivanhoe Mines announced that underground development at the Kamoa-Kakula Copper Project totalled 2,069 metres in September, setting a new monthly record for the project and bringing the total underground development to more than 22.6 kilometres – approximately 7.0 kilometres, or 44% ahead of schedule.



A Floatation platform lift during construction of the initial Kakula Copper Mine

The project’s monthly total of 2,069 metres of underground development is comprised of 1,696 metres at the Kakula Mine and 373 metres at the Kansoko Mine, which is located at the Kamoa Deposit – approximately 10 kilometres north of the Kakula Mine.

Several underground development headings at the Kakula Mine now have transitioned into the higher-grade ore zones near the centre of the deposit, grading between approximately +5% copper and +8% copper. October will be the first month of mining in Kakula’s high-grade ore from the southern access drives, and this ore will be stored on a separate high-grade surface stockpile near the southern decline. Mining on the northern side of the orebody also will soon intersect the higher grade ore.

The main access drives between northern and southern declines have less than 520 metres remaining before they connect in the high-grade centre of the deposit. The connection is expected to occur next month and will significantly increase ventilation to the centre of the orebody, allowing for additional mining crews to begin work in Kakula’s high-grade ore zones.


The Kakula Copper Mine in the Democratic Republic of Congo (DRC) is on track for first production in Q3 2021

In addition to driving the main connecting access drives, underground mining crews at Kakula are focused on preparation work for developing the high grade, drift-and-fill stoping blocks in the centre of the orebody, where the average grade is up to +8% copper. Opening up of the mining footprint for these high-grade stoping areas entails development work in areas of low-, medium- and high-grade ore, and is designed to coincide with the start-up of the processing plant next year. This will allow mining crews to deliver high-grade stoping ore directly from the underground to the processing plant.

L’abattage avec percement et remblayage est une forme ultra-efficace d’exploitation minière mécanisée souterraine et permettra à l’exploitation de récupérer nettement plus de tonnes du corps minéralisé. Once drift-and-fill stoping operations begin, mining at the Kakula Mine will produce a significantly higher proportion of high-grade stoping ore than lower-grade development ore.

Underground development at the Kansoko Mine currently is in low-to-medium-grade ore zones, grading between approximately +2% and +3% copper. Kansoko is being developed by training crews and will be a supplemental source of ore when the Kakula concentrator processing capacity doubles to 7.6 Mtpa − currently planned to be commissioned in Q2 2022.

Pre-production surface ore stockpiles now total more than 803,000 tonnes

In September, mining crews at the Kakula and Kansoko mines produced and transported to surface approximately 132,000 tonnes of ore, bringing the project’s total pre-production ore stockpiles to an estimated 803,000 tonnes. September’s ore production is approximately 24% higher than August.


Aerial view of the Kakula North stockpile

The ore being mined from the northern portion of the Kakula Mine is transported to surface via the conveyor system and placed on a blended surface stockpile that now contains 540,000 tonnes grading an estimated 3.73% copper; comprised of 125,000 tonnes of high-grade ore grading 6.00% copper, and 415,000 tonnes of medium-grade ore grading 3.05% copper.

Two additional, pre-production ore stockpiles are located at the Kakula South decline (approximately 168,000 tonnes grading 2.73% copper) and the Kansoko decline (approximately 95,000 tonnes grading 2.34% copper).

Kamoa-Kakula Integrated Development Plan 2020 (IDP 2020)

In septembre 2020, Ivanhoe Mines announced extremely positive findings of an independent definitive feasibility study (DFS) for the development of the Kakula Copper Mine; together with an updated pre-feasibility study (PFS) that includes ore mined from the nearby Kansoko Copper Mine in addition to ore mined from Kakula; and an updated, expanded preliminary economic assessment (PEA) for the overall development plan of all the copper discoveries made to date at the Kamoa-Kakula Project on the Central African Copperbelt in the DRC.

The DFS, PFS and updated PEA, collectively referred to as the Kamoa-Kakula Integrated Development Plan 2020 (Kamoa-Kakula IDP20), build on the excellent results of the previous studies announced in février 2019. The new DFS incorporates the advancement of development and construction activities to date, and has once again confirmed the outstanding economics of the first phase Kakula Mine. As well, the expanded PEA shows the excellent potential to develop the project to a much larger scale and with a significantly larger production capacity.


Licence minière Kamoa-Kakula, indiquant les zones de ressources minérales de Kamoa, Kamoa Nord, Kakula et Kakula Ouest, ainsi qu’une partie de la zone d’avenir occidentale appartenant à 100% à Ivanhoe.

The Kamoa-Kakula Integrated Development Plan 2020 encompasses three development scenarios:

  • Definitive feasibility study for stage one Kakula Mine development. The Kakula 2020 DFS evaluates the development of a stage one, 6-Mtpa underground mine and surface processing complex at the Kakula Deposit with a capacity of 7.6 Mtpa, built in two modules of 3.8 Mtpa, with the first already under advanced construction.
  • Pre-feasibility study including Kansoko Mine development. The Kakula-Kansoko 2020 PFS evaluates the development of mining activities at the Kansoko Deposit in addition to the Kakula Mine, initially at a rate of 1.6 Mtpa to fill the concentrator at Kakula, eventually ramping up to 6 Mtpa as the reserves at Kakula are depleted.
  • Expanded, subsequent development to four producing mines. The Kamoa-Kakula 2020 PEA includes an analysis of the potential for an integrated, 19-Mtpa, multi-stage development, beginning with initial production from the Kakula Mine, to be followed by subsequent, separate underground mining operations at the nearby Kansoko, Kakula West and Kamoa North mines, along with the construction of a direct-to-blister smelter. The Kamoa North Area comprises five separate mines that would be developed as resources are mined out elsewhere, to maintain the production rate at up to 19 Mtpa, with an overall life in excess of 40 years.

The Kamoa-Kakula IDP20, which includes the Kakula 2020 DFS, Kakula-Kansoko 2020 PFS and Kamoa-Kakula 2020 PEA, was independently prepared on a 100%-basis by OreWin Pty Ltd. of Adelaide, Australia; China Nerin Engineering Co., Ltd., of Jiangxi, China; DRA Global of Johannesburg, South Africa; Epoch Resources of Johannesburg, South Africa; Golder Associates Africa of Midrand, South Africa; KGHM Cuprum R&D Centre Ltd. of Wroclaw, Poland; Outotec Oyj of Helsinki, Finland; Paterson and Cooke of Cape Town, South Africa; Stantec Consulting International LLC of Phoenix, USA; SRK Consulting Inc. of Johannesburg, South Africa; and Wood plc of Reno, USA.


Mill construction during development of the initial Kakula Copper Mine

The Kamoa-Kakula 2020 PEA is preliminary in nature and includes an economic analysis that is based, in part, on Inferred Mineral Resources. Inferred Mineral Resources are considered too speculative geologically for the application of economic considerations that would allow them to be categorized as Mineral Reserves – and there is no certainty that the results will be realized. Les ressources minérales ne démontrent pas de viabilité économique et ne constituent pas des réserves minérales.

Modular, integrated, expanded development option potential for the Kakula and Kamoa deposits, mining a total of 19 Mtpa, with construction of a direct-to-blister smelter

  • The Kamoa-Kakula 2020 PEA presents an additional development option of a multi-stage, sequential operation on Kamoa-Kakula’s high-grade copper deposits.
  • Initial production from the Kakula Mine at a rate of 6 Mtpa, followed by subsequent, separate underground mining operations at the nearby Kansoko, Kakula West and Kamoa North mines, along with the construction of a direct-to-blister smelter. The Kamoa North Area comprises five separate mines that will be developed as resources are mined out elsewhere, to maintain the production rate at up to 19 Mtpa, with an overall life in excess of 40 years.
  • For the integrated, 19-Mtpa, multi-stage development, the PEA envisages US$0.7 billion in remaining initial capital costs. Future expansion at the Kansoko Mine, Kakula West Mine and Kamoa North mines would be funded by cash flows from the Kakula Mine, resulting in an after-tax net present value at an 8% discount rate (NPV8%) of US$11.1 billion, an internal rate of return of 56.2%, and a payback period of 3.6 years.
  • Ivanhoe’s proportional share of the remaining initial capital cost of this option is approximately US$0.36 billion for the Kamoa-Kakula 2020 PEA.
  • Under this approach, the PEA also contemplates the construction of a direct-to-blister copper smelter at the Kakula plant site with a capacity to process one million tonnes of copper concentrate per annum to be funded from internal cash flows. Cela interviendrait dans la cinquième année d’exploitation, et produirait des économiques significatives sur les frais de traitement et les coûts de transport.
  • The 19-Mtpa scenario shows the potential for average annual production of 501,000 tonnes of copper at a total cash cost of US$1.07/lb. copper during the first 10 years of operations and production of 805,000 tonnes of copper by year 8. Le taux de production envisagé ferait de Kamoa-Kakula la deuxième mine de cuivre au monde.

Figure 1. Kamoa-Kakula 19-Mtpa PEA long-term development plan.

Figure by OreWin 2020.

Figure 2. Overview of deposits included within the Kakula 2020 DFS(6 Mtpa ─ outlined by blue dotted line), Kakula-Kansoko 2020 PFS (7.6 Mtpa ─ outlined by purple dotted line) and Kamoa-Kakula 2020 PEA (outlined by green dotted line).

Figure by OreWin 2020.

Key initial projections from the Kakula 2020 DFS

The study evaluates the development of a stage one, 6-Mtpa underground mine and surface processing complex at the Kakula Deposit of 7.6 Mtpa, built in two modules of 3.8 Mtpa, with the first already under advanced construction. The first module of 3.8 Mtpa commences production in Q3 2021, and the second in Q1 2023. The life-of-mine production scenario provides for 110 million tonnes to be mined at an average grade of 5.22% copper, producing 8.5 million tonnes of high-grade copper concentrate, containing approximately 10.8 billion pounds of copper.

The economic analysis uses a consensus, real long-term copper price of US$3.10/lb. (excluding inflation) and returns an after-tax NPV at an 8% discount rate of US$5.5 billion. It has an after-tax IRR of 77.0% and a payback period of 2.3 years.

The estimated remaining initial capital cost, including contingency, is US$0.65 billion from 1 Juillet 2020. The capital expenditure for off-site power, which is included in the remaining initial capital cost, includes advances to the DRC state-owned electricity company, Société Nationale d'Electricité (SNEL), to upgrade two hydropower plants (Koni and Mwadingusha) to provide the Kamoa-Kakula Project with access to clean electricity for its planned operations. The hydro-power upgrading work is being led by Stucky Ltd., of Renens, Switzerland, and the advance payments will be recovered by Kamoa-Kakula through a reduction in the power tariffs paid.

Aerial picture of the Mwadingusha hydro-electric dam and power plant, with the new installed penstocks. Mwadingusha will soon be delivering 72 megawatts (MW) of clean, sustainable hydro-electricity to the national grid. The Kakula Mine is scheduled to be energized with permanent, 220-kilovolt (kV), hydro-generated power from the national grid in early 2021.

Expanded 19-Mtpa development scenario for the Kakula and Kamoa deposits

The Kamoa-Kakula 2020 PEA also assesses an additional development option of mining several deposits on the Kamoa-Kakula Project as an integrated, 19-Mtpa mining, processing and smelting complex, built in multiple stages. This scenario envisages the construction and operation of three separate mines: first, an initial 6-Mtpa mining operation would be established at the Kakula Mine on the Kakula Deposit; this is followed by a subsequent, separate 6-Mtpa mining operation at the Kansoko Mine, where two crews are working already; a third 6-Mtpa mine then will be established at the Kakula West Mine, in addition to a fourth initial mine in the Kamoa North area operating initially at 1 Mtpa. The processing plant is constructed in five modules of 3.8 Mtpa, with an ultimate capacity of 19 Mtpa.

As the resources at the Kakula, Kansoko and Kakula West mines are mined out, production would begin sequentially at five other mines in the Kamoa North area to maintain throughput of 19 Mtpa to the then existing concentrator and smelter complex, as illustrated in Figure 1.

Each mining operation is expected to be a separate underground mine with a shared processing facility and surface infrastructure located at Kakula. Material will be transported to the Kakula processing complex by a system of overland conveyors. Included in this scenario is the construction of a direct-to-blister copper smelter with a capacity of one million tonnes of copper concentrate per annum.

The Kamoa-Kakula 2020 PEA is preliminary in nature and includes an economic analysis that is based, in part, on Inferred Mineral Resources. Inferred Mineral Resources are considered too speculative geologically for the application of economic considerations that would allow them to be categorized as Mineral Reserves – and there is no certainty that the results will be realized. Les ressources minérales ne démontrent pas de viabilité économique et ne constituent pas des réserves minérales.

Ultra-high-grade drill core, comprised almost entirely of chalcocite, from a hole drilled at Kamoa North. Kamoa North is an important source of high-grade ore in Kamoa-Kakula’s expanded 19 Mtpa development scenario. Chalcocite has the greatest percentage of copper of all the common sulphide-copper-bearing minerals ─ almost 80% copper by weight.

Summary of the PEA’s key results for the 19-Mtpa development scenario

  1. Very-high-grade initial phase projected to have a grade of 6.8% copper in the first year of production and an average grade of 5.1% copper during the first 10 years of operations, resulting in estimated average annual copper production of 501,000 tonnes.
  1. Recovered copper production is estimated at805,000 tonnes in year 8, which would rank the Kamoa-Kakula Project as the second largest copper producer in the world.
  1. Remaining initial capital cost, including contingency, is US$0.71 billion, with subsequent expansions at Kansoko, Kakula West, and other mining areas, as well as the smelter, to be fundedbycash flows from the Kakula Mine.
  1. Average total cash costs of US$1.07/lb. copper during the first 10 years, including sulphuric acid credits.
  1. After-tax NPV, at an 8% discount rate, of US$11.1 billion.
  1. After-tax IRR of 56.2% and a payback period of 3.6 years.

Kamoa-Kakula Project 2020 Mineral Reserve

ClassificationOre (Mt)Cuivre (%)CuivreCuivre
(Mlb contenus)(kt contenus)
Proven Kakula Mineral Reserve
Probable Kakula Mineral Reserve1105,2212 6655 745
Proven Kansoko Mineral Reserve
Probable Kansoko Mineral Reserve1253,8110 5254 774
Proven Kamoa-Kakula Mineral Reserve
Probable Kamoa-Kakula Mineral Reserve235 4,47 23 190 10 519

Notes to accompany Kamoa-Kakula Project 2020 Mineral Reserve table:

  1. The real long term copper price used for calculating the financial analysis is US$3.10/lb. Les calculs de l’analyse ont été effectués sur la base d’hypothèses concernant les coûts d’affinage et de transformation en fonderie, les conditions de paiement et déductions, le transport du concentré, les taux de récupération métallurgique et les redevances.
  2. For mine planning, the copper price used to calculate block model Net Smelter Returns (NSRs) was US$3.00/lb. for Kansoko and US$3.10/lb. for Kakula.
  3. Une limite accrue des revenus net de fonderie, soit 100,00 USD/t, a été utilisée pour définir les blocs d’abattage. Une limite marginale des revenus net de fonderie, soit 80,00 USD/t, a été utilisée pour définir le minerai et les rejets. 
  4. Les ressources minérales indiquées ont été utilisées pour les réserves minérales probables. 
  5. Pour l’estimation des tonnages et des teneurs, des considérations concernant la dilution et la récupération ont été prises en compte.
  6. Les réserves minérales présentées ci-dessus ne peuvent être ajoutées aux ressources minérales.

Ressources minérales consolidées de Kamoa et Kakula en 2020

En février 2020, Ivanhoe a annoncé une estimation mise à jour des ressources minérales indiquées et présumées pour le gisement de Kamoa qui inclut les ressources dans la nouvelle zone de Kamoa North Bonanza et la zone de Kamoa Far North. La date d’entrée en vigueur de la nouvelle estimation des ressources minérales de Kamoa est le 30 janvier 2020 ; l’estimation a été préparée par George Gilchrist, vice-président des ressources minérales d’Ivanhoe Mines, sous la direction de Gordon Seibel, membre agréé de la Society of Mining, Metallurgy and Exploration, du groupe Wood (anciennement Amec Foster Wheeler) de Reno, États-Unis, et est déclarée conforme aux Normes de définition CIM 2014 pour les ressources minérales et les réserves minérales. M. Siebel est la personne qualifiée pour l’estimation.

L’équipe géologique du projet a également mis à jour l’estimation des ressources minérales pour le gisement Kakula. La date d’entrée en vigueur de cette estimation mise à jour est novembre 2018. Les ressources minérales indiquées et présumées totales pour le projet de Kamoa-Kakula en vigueur le 30 janvier 2020, sont indiquées au tableau 8. Des tableaux présentant les ressources minérales indiquées et présumées séparément pour les gisements Kamoa et Kakula, ainsi que la sensibilité des ressources minérales à la teneur de coupure sont présentés dans les annexes de ce communiqué

Tableau 8. Ressources minérales totales indiquées et présumées de Kamoa et de Kakula (à une teneur totale en cuivre de 1%).

GisementCatégorieTonnes
(millions)
Région
(km²)
Teneur en cuivre
(%)
Épaisseur verticale
(m)
Cuivre contenu
(kt)
Cuivre contenu
(milliard de livres)
KamoaIndiquées76055,22,735,020 80045,8
Inférées23521,81,704,04 0108,8
KakulaIndiquées62721,72,7410,317 20037,9
Inférées1045,61,616,71 6803,7
Total Projet Kamoa-KakulaIndiquées1 38777,02,746,538 00083,7
Inférées33927,41,684,55 69012,5

Notes afférentes au tableau « Ressources minérales totales et combinées de Kamoa et Kakulajanvier 2020 » :

  1. Le vice-président des ressources d’Ivanhoe, George Gilchrist, membre de la Société de géologie de l’Afrique du Sud et scientifique naturel professionnel (Pr. Sci. Nat) et du Conseil sud-africain des professions scientifiques naturelles (SACNASP), a estimé les ressources minérales sous la supervision de Gordon Seibel, membre agréé (RM) de la Society of Mining, Metallurgy and Exploration (SME), employé du groupe Wood, et personne qui est qualifiée pour l’estimation des ressources minérales. La date d'entrée en vigueur de l’estimation est le 30 janvier 2020 et la date limite pour les données de forage est le 20 janvier 2020. Les ressources minérales estimées respectent les normes de définition des ressources et des réserves minérales 2014 de l’ICM. Les ressources minérales incluent 100 % des réserves minérales.
  2. Les Ressources minérales sont présentées sur la base d’une teneur de coupure en cuivre total (TCu) de 1 % et d’une épaisseur verticale minimale de 3 mètres (m). Ces perspectives sont raisonnables pour une extraction économique éventuelle dans l’hypothèse d’un prix du cuivre de 3,00 $US/livre, l’utilisation des méthodes de chambre et piliers et de percement et remblayage, et la vente des concentrés de cuivre produits à une fonderie. Les coûts d’exploration sont estimés à 27 USD/tonne. Le coût du concentrateur, du traitement des résidus miniers ainsi que les dépenses administratives et frais généraux sont estimés à 17 USD/tonne. Le taux de récupération métallurgique est estimé en moyenne à 84 % (86 % pour l’hypogène et 81 % pour le supergène). La teneur de coupure en cuivre total (TCu) de 1 %, qui suppose des revenus nets de fonderie pour 100 % des blocs de ressources minérales couvrira le traitement, le traitement des résidus miniers, les dépenses administratives et frais généraux.
  3. Les ressources minérales déclarées ne prévoient aucune perte ou dilution au contact des épontes inférieures ou supérieures. Aucune récupération d’exploitation minière n’a été appliquée.
  4. La profondeur de la minéralisation sous la surface varie de 10 m à 1 320 m pour les ressources minérales indiquées et de 20 m à 1 560 m pour les ressources minérales présumées.
  5. Les espacements approximatifs des trous de forage est de 800 m pour les ressources minérales inférées et 400 m pour les ressources minérales indiquées.
  6. Le pendage moyen du gisement dans les contours des ressources minérales indiquées et inférées est de 12,7 degrés. L’épaisseur verticale approche l’épaisseur réelle à Kamoa.
  7. Ces chiffres sont arrondis tel que prescrit par les directives applicables, ce qui peut donner lieu à d’apparentes différences entre les chiffres indiquant le tonnage, la teneur ou le contenu en métal.
  8. Le vice-président des ressources d’Ivanhoe, George Gilchrist, membre de la Société de géologie de l’Afrique du Sud et scientifique naturel professionnel (Pr. Sci. Nat) et du Conseil sud-africain des professions scientifiques naturelles (SACNASP), a estimé les ressources minérales de Kakula sous la supervision de Gordon Seibel, membre agréé (RM) de la Society of Mining, Metallurgy and Exploration (SME), employé du groupe Wood, et personne qui est qualifiée pour les ressources minérales. La date effective de l’estimation de Kakula est le 10 novembre 2018, et la date de coupure pour les données de forage est le 1 novembre 2018. Les ressources minérales ont été estimées suivant les normes de l’ICM en matière de définition des Ressources et Réserves minérales (2014) et sont reportées sur une base 100 %. Les ressources minérales incluent 100 % des réserves minérales.
  9. Les Ressources minérales sont présentées sur la base d’une teneur de coupure en cuivre total (TCu) de 1 % et d’une épaisseur minimale approximative de 3 mètres (m). Ces perspectives sont raisonnables pour une extraction économique éventuelle dans l’hypothèse d’un prix du cuivre de 3,00 $US/livre, l’utilisation des méthodes de chambre et piliers et de percement et remblayage, et la vente des concentrés de cuivre produits à une fonderie. Les coûts d’exploration sont estimées à 42 $US/tonnes. Le coût du concentrateur, du traitement des résidus miniers et les frais généraux et dépenses administratives sont estimés à 18 $US/t. Le taux récupération métallurgique est supposé atteindre en moyenne 85 %. Ivanhoe étudie actuellement la possibilité de réduire les coûts d’exploitation minière en utilisant une méthode de chambres et piliers à convergence contrôlée. Avec une teneur de coupure en cuivre total (TCu) de 1 %, les revenus nets de fonderie de 100 % des blocs de Ressources minérales couvriront les coûts de concentration et de traitement des résidus miniers, et les dépenses administratives et frais généraux.
  10. Les ressources minérales déclarées ne tiennent pas compte des pertes ou dilutions au contact des épontes inférieures ou supérieures. Aucune récupération d’exploitation minière n’a été appliquée.
  11. Les espacements approximatifs des trous de forage est de 800 m pour les ressources minérales inférées et de 400 m pour les ressources minérales indiquées.
  12. Le pendage moyen du gisement dans les contours des ressources minérales indiquées et inférées est de 17,8 degrés. L’épaisseur verticale approche l’épaisseur réelle à Kakula.
  13. Ces chiffres sont arrondis tel que prescrit par les directives applicables, ce qui peut donner lieu à d’apparentes différences entre les chiffres indiquant le tonnage, la teneur ou le métal contenu.

Les tonnages et les teneurs ont été calculés pour les blocs d’exploitation minière, et des considérations de dilution et de récupération d’exploitation minière non prévues ont été prises en compte dans l’élaboration de l’énoncé des réserves minérales.

Cliquez ici pour voir le rapport technique complet intitulé : Kamoa-Kakula 2018 Resource Update, mars 2018

Cliquez ici pour voir l’évaluation économique préliminaire 2016 de Kakula, janvier 2017

Alors qu'Ivanhoe Mines et son partenaire dans la coentreprise, Zijin Mining, continuent de faire progresser la construction de la mine de cuivre Kakula en République démocratique du Congo, Ivanhoe est heureux de présenter une courte vidéo d'animation montrant le projet de développement de la mine de six millions de tonnes. minière (6 Mtpa) par an et les installations de traitement de surface.

Le projet de Kamoa-Kakula transforme les communautés locales grâce à l’agriculture durable, la pisciculture et les opportunités d’emploi. Regardez la vidéo ci-dessous pour en savoir plus sur le programme de soutien aux moyens de subsistance durable de Kamoa-Kakula.

En mars 2015, l’équipe d’exploration d’Ivanhoe a reçu le prix 2015 PDAC Thayer Lindsley International Discovery Award de l’Association canadienne des prospecteurs et entrepreneurs, pour la mine de Kamoa

Rapports d’impact environnemental

Projet Kamoa-Kakula - Étude d’impact environnemental mise à jour en juin 2017Cliquez ici pour afficher le PDF

Inscrivez-vous à notre liste d’e-mails

Powered by Translations.com GlobalLink OneLink Software